|
|
|
DECEMBER REPORTS
2009
EQUIPMENT SERVICES: # 1, # 9, # 60, # 71
EQUIPMENT REPAIRS: # 1- 4 NEW 255X75X17 TIRE, NEW WIPER BLADES. # 2- WIPER BLADES REPLACED. # 17- FIRE HOSE REPAIRS, REEL SWIVEL REPLACEMENT. # 21- HYDRAULIC STEEL LINE TO ARM CYLINDER REPLACED. # 24- FRONT WHEEL DRIVE ASSIST DRIVE LINE, SPLINED TRANSMISSION GEAR REPLACED, SWING PIN HOLES BORED AND NEW BUSHINGS AND PINS REPLACED. # 56- BOX SCRAPER BLADE REPLACED. # 71- ONE NEW 1400X24 TIRE MOUNTED. # 95- 2 NEW TRACTION TIRES REPLACED (1100X24.5).
CANAL MAINTENANCE
STORAGE CANAL: THE BRIDGE FLOOR AND RAILING WAS FINISHED AT THE HEAD GATES. NEW GRAVEL AND REFLECTIVE TAPE WAS PUT AT THE ENDS. THE OLD WASTEWAY RADIALS WERE CUT UP AND SOLD FOR SCRAP. WORK AT THE FUSE PLUG AREA WAS REQUIRED AS THE HIGHER FLOWS AT THE BEGINNING OF WINTER WATER STORAGE BEGAN TO FLOW OVER THE CONCRETE OR SO WE THOUGHT. MOST OF THE OVERFLOW WAS PIPING UNDERNEATH THE CONCRETE STRUCTURE FROM THE WEST END TO THE EAST END OF THE NORTH STRUCTURE. CONCRETE AND DIRT WERE HAULED IN TO REPAIR THE LEAK AND STOP THE PIPING. HIGHER FLOWS AND DITCH PRESSURE CAUSED THE PIPING TO REOCCUR. THE DRAIN GATE AREA WAS REPACKED AND ALSO RIPRAPPED HIGHER UP ON THE DITCH. THE HOLBROOK SIPHON HAS BEEN CLEANED OUT SEVERAL TIMES IN THE PAST FEW WEEKS. NOW THAT THE WATER HAS LEVELED OFF NEAR 338 CFS THE TRASH AND DEBRIS HAVE CLEARED UP. THE SERVICE ROAD NEAR THE TIMBER LAKE INLET WAS REBLADED. THE CONCRETE WALL AT “ADOBARCO” WAS POURED DURING THE MONTH.
LA JUNTA DIVISION: A CONCRETE DITCH FROM THE KNOLL FARM WAS HAULED OFF FOR RIPRAP ALONG THE SERVICE AREA NEARBY. CONCRETE RIPRAP WAS HAULED TO WASTEWAY ONE WASHES ALONG THE SERVICE ROAD. SERVICE ROADS WERE BLADED WITHIN THE HEAD GATE AREA. SIX HEAD GATES WILL BE REPLACED IN THE FOLLOWING MONTHS. THE HORSE CREEK SIPHON WILL BE CHECKED FOR REPAIRS AND THE OVERFLOW GATES WILL BE PART OF WINTER WORK
LAS ANIMAS DIVISION: CURRENTLY, THE CREW IS HAULING OFF THE OLD HOUSE FROM THE NEWLY PURCHASED PROPERTY. CLEAN-UP WILL TAKE A FEW DAYS. BACKFILL SOIL AND GRAVEL WILL COVER THE NEW LOT. ROCK AND CONCRETE FROM THE OLD HIGH SCHOOL IS SET TO BE HAULED AWAY IN MID-DECEMBER. FOUR HEADGATES WILL BE REPLACED THIS WINTER.ALONG WITH REPAIRS TO ALL OF THE CHECKS.
LIMESTONE DIVISION: FLOW METERS ARE CURRENTLY BEING CHECKED OUT FOR REPAIR. 160 AND 172 HEAD GATES WILL BE REPLACED THIS WINTER. SEVERAL CHECKS WILL GET EXTENSIVE REPAIR WORK. JETTY WORK WEST OF ROAD 30 IS ALSO PLANNED.
LAMAR DIVISION: 134G AND 251D HEAD GATES WILL BE REPLACED ALONG WITH WELDING REPAIRS TO SEVERAL OF THE CHECKS.
NOVEMBER REPORTS
2009
EQUIPMENT SERVICES: # 2, # 8, # 17, # 21, # 68
EQUIPMENT REPAIRS: # 2- FRONT BRAKES, BOTH ROTORS TURNED, # 8- REAR BRAKES, # 17- ANTI-FREEZE REPLACED, # 22- REPLACE BATTERIES, #48- FLUSH RADIATOR, ADD NEW ANTI-FREEZE, # 68- REPAIR HYDRAULIC HOSE, #86- REPLACE TWO AIR BAGS
CANAL MAINTENANCE
STORAGE CANAL: A NEW DRAIN GATE HAS BEEN PUT IN NEAR THE HORSE CREEK PLUG TO KEEP WATER FROM BUILDING UP ON THE PLUG WALL DURING SUMMER RAINS. THE PLUG WASHED OUT ONCE DURING THE SUMMER AND CAME CLOSE ANOTHER TIME. THE NEW, WIDER BRIDGE FLOOR AT THE HEADGATES IS FINISHING CURE TIME WHILE THE RAILING IS BEING PUT UP. THE BLADDER DAM HAS BEEN RAISED AND WASHED OF SAND BUILD- UP. THE NEW RADIAL GATES ARE RAISED AND WATER IS FLOWING BACK TO THE RIVER VIA THE WASTEWAY. THE ADOBE RESERVOIR BUBBLER IS ON LINE AGAIN AFTER BEING DOWN FOR ABOUT 4 MONTHS. THE MUFFLER AT THE WATERS END OF ORIFICE LINE BECAME SEDIMENT PLUGGED. THE NEW SATELLITE SITE AT ADOBE CREEK ABOVE THE RESERVOIR WILL COME ON LINE FOR 11/5/09 TO TEST THE EQUIPMENT. IT WILL BE READY FOR THE COMING IRRIGATION SEASON. A NEW SIDE WALL ON THE NEW STAFF GAGE SIDE AT ADOBARCO WILL BE POURED WITHIN THE NEXT FEW DAYS .
LAJUNTA DIVISION: OTHER THAN CLEANING IN FRONT OF WEIRS AND HAULING SAND NO OTHER WORK WAS DONE IN THE DIVISION THIS MONTH.
LASANIMAS DIVISION: CLEANING IN FRONT OF WEIR BOXES AND SOME SAND HAULING TOOK PLACE DURING THE MONTH.
LIMESTONE DIVISION: CLEANING IN FRONT OF WEIR BOXES AND SOME SAND HAULING WERE DONE AS MOST OF THE MONTHS WORK TOOK PLACE ON THE STORAGE SYSTEM.
LAMAR DIVISION: CLEANING IN FRONT OF WEIRS AND CLEARING THE BASIN INLET OF TRASH WERE THE MAIN WORK DONE IN THE DIVISION FOR THE MONTH.
WATER: THIS HAS BEEN A VERY GOOD FOUR WEEKS WITH RAIN AND SNOW SHOWERS PLUS THE RIVER RAISING ENOUGH TO ALLOW US TO BE NEAR OR AT OUR SECOND DECREE EVEN BEFORE DISTRICT 67 WENT OUT ON 11/1/09. WE WERE LOOKING AT FINISHING WITH 25 RUNS AND NOW IT LOOKS LIKE WE COULD END WITH 33 RUNS. THE YOUNG HAY AND NEW WHEAT SHOULD GET A GREAT JUMP START FROM THIS FALL MOISTURE.
|
|
|